Title Construction Complete on Vietnam's Largest Onshore Wind Project
Source Other
Date 2018-11-08 PM 6:22:07 Hit 38
Contents
 

Wind energy developer The Blue Circle has completed construction of Phase 2 of the Dam Nai Project in Ninh Thuan Province, South Vietnam.

 

The first phase - comprising three G114-2.625-MW turbines from Siemens-Gamesa was completed in October 2017.

 

By adding 12 turbines this year to the original three, the Dam Nai Project is now the largest onshore wind power plant constructed in Vietnam, with 40 MW installed capacity. Commissioning of the turbines will take place this month and commercial operations are expected to start in December.

 

 

...

 

For more information, refer to the original document by clicking the source.


 
 